The project involves the construction of 45 wind turbines that will be capable of producing 202.5 Mw of power. A positive investment decision was announced on December 3, 2019, and construction began in late December 2019. Construction was deferred in May 2020 for the remainder of the year due to market conditions associated with the covid-19 pandemic. Construction resumed in April 2021.
The project involves the construction of 45 wind turbines that will be capable of producing 202.5 Mw of power. A positive investment decision was announced on December 3, 2019, and construction began in late December 2019.
Construction was deferred in May 2020 for the remainder of the year due to market conditions associated with the covid-19 pandemic. Construction resumed in April 2021.