Replacing an existing 86cm diameter pipe with a 91cm pipe. The project will increase pipeline capacity from Alberta by 370,000 barrels per day. Alberta's portion of cost is $4.2B.Construction commenced in August 2017, and the Canadian portion came online in 2020, the full project was completed by October 1, 2021.